Project start date: 20-07-10
Project completion date: 20-07-11
Duration: 12 months
WORKPACKAGES | Month | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
1: Project Management | x | x | x | x | x | x | x | x | x | x | x | x | |
2: Advocacy | x | x | x | x | x | x | x | x | x | x | x | x | |
3: Workshops/Training | x | x | x | x | x | x | x | ||||||
4: User Survey | x | x | x | x | x | x | x | x | |||||
5: Community Engagement | x | x | x | x | x | x | x | x | x | x | |||
6: Evaluation and Quality Assurance | x | x | x | x | x | x | |||||||
7: Dissemination | x | x | x |
Project management will be based on JISC guidelines, and will therefore follow a lightweight PRINCE2-style methodology. Project management techniques will be of a modest level of complexity, in keeping with the size and scale of the project and the work involved.